Standard builds run four to six weeks from approved drawings. Here is what drives that number.
| Engineering and approval drawings | 3–5 business days |
|---|---|
| Material release (breakers, steel) | 1–2 weeks |
| Fabrication and assembly | 2–3 weeks |
| Testing and labeling | 2–3 days |
| Freight | 1–5 days by destination |
When a plant is down, call (951) 403-5738. If the frame and breakers are in stock we can compress the schedule significantly.
Send your single-line or tell us the service size. We reply with pricing, lead time and a drawing schedule.